|
Conference Papers | 1999 Conference Papers
COMBINING
CMF, OZONE AND BAC - THE TRENTHAM EXPERIENCE
C.Nash
Project Sales Manager,
USF Australia Pty Ltd
J.Stewart Project
Manager,
Coliban Water Authority
M. Muntisov Nat.
Manager -Water Quality and Treatment,
Gutteridge Haskins & Davey Pty Ltd
DOWNLOAD
(pdf
49K)
ABSTRACT
The
Trentham Water Treatment Plant combines a unique combination
of Continuous Microfiltration (CMF) , Ozone and Granular
Activated Carbon to treat a variable and difficult raw
water supply. Whilst standby chemical coagulant dosing
is installed at Trentham, it has not been used since
commissioning in February 1998. Without chemical coagulant
addition the treated water quality from the plant has
exceeded all Coliban Water's performance criteria. The
combination of technologies has presented some interesting
outcomes from an operational point of view. These include
the biological management of the activated carbon and
management of backwash flows.
1.0
INTRODUCTION
The
town of Trentham in Victoria has a population of 600
and is located approximately one hour north of Melbourne.
Its
water supply is derived from springs which feed two
reservoirs with a combined capacity of 70ML. The raw
water supply was previously chloraminated prior to delivery
to Trentham.
Typical raw water quality is set out in Table 1. The
water can be characterised as being low in colour and
turbidity with moderate hardness and alkalinity. Seasonal
problems occur with algal derived tastes and odours,
and iron and manganese levels are sufficiently elevated
to cause nuisance dirty water complaints.
Coliban
Water, the responsible water authority, took over the
Trentham system in the recent restructuring of the Victorian
water industry. It was concerned over the periods of
poor water quality with complaints of discoloured water
and offensive tastes and odours. Coliban Water called
tenders for a new treatment plant to be implemented
under a design and construct contract to solve these
water quality problems. In addition, Coliban Water also
specified stringent requirements on algal toxin destruction
and protozoan cyst removal.
USF
Australia Pty Ltd with the assistance of Gutteridge
Haskins & Davey (GHD) were awarded the contract. The
accepted treatment process was a unique combination
of microfiltration, ozonation and granular activated
carbon filtration which permitted satisfactory operation
without the need for chemical coagulants under typical
raw water conditions. To handle conditions outside the
typical range, particularly for colour, a polyaluminium
chloride dosing facility is provided for short term
operation under these circumstances.
Table
1: Raw Water
Quality

2.0 PLANT
DESCRIPTION AND COSTS
Plant
Description
A
general schematic of the treatment plant is shown in
Figure 1.
Figure
1 : General Schematic Trentham
WTP

Raw
water is pumped from the existing reservoirs to a 25kL
tank at the treatment plant.
The
microfiltration unit is a US FilterMemcor 16M10C using
nominal 0.2 micron pore size polypropylene hollow fibres.
Automatic air/water backwashing and clean-in-place systems
are provided.
The
microfiltered water is delivered under pressure to a
pressurised ozone contact tank. Ozone is generated on
site from air and injected at the inlet to the ozone
contact tank via a service water stream.
The
ozonated water is then uniformly applied to an upflow
GAC filter vessel with an empty bed contact time of
15 minutes and using coal-based carbon. The GAC filter
is backwashed by a combination of ozonated and treated
water. GAC washwater is collected in the microfiltration
feed tank and is thus retreated within the process.
GAC
filtered water is discharged to a 0.7 ML clear water
storage. Provision has been made for sodium hypochlorite
dosing at the clear water storage inlet. The outflow
from the clear water storage is disinfected using the
existing chloramination system.
Some
unusual features of the plant include:
- full
process reversibility. It is possible to alter the
process sequence and run ozonation/GAC ahead of microfiltration.
- a
stabilisation period is provided for the GAC filter
immediately after backwashing to allow its performance
to stabilise before it is brought back into service.
- automatic
recirculation through the GAC filter occurs if the
plant is off-line for more than a preset period of
time to prevent the filter from going 'off'.
A
summary of the main plant design parameters is presented
in Table 2.
Table
2: Design Parameters

Costs
The
construction cost of the Trentham plant was around $700,000
including 700 kL clear water storage tank, connecting
pipework to and from the existing Reservoir outlet and
delivery pumping station.
Operating
costs have not yet been fully defined but are estimated
to be of the order of $24,000 pa. including labour,
parts, maintenance and membranes. Annual treated water
production is of the order of 130 ML.
3.0 PERFORMANCE
The
plant has been in operation since February 1998. In
the sixteen months of operation some key operational
knowledge of this type of system has been gained. This
can be summarised as follows:
- The
plant has operated in the CMF, Ozone and GAC process
order. There has been no need to use Ozone/GAC as
the first stage.
- Taste
and Odour removal has met all Coliban Water's requirements.
- Treated
water turbidity has been constantly low (see Figure
1 below).
- True
colour removal has been outstanding without the need
to add a chemical coagulant ahead of the CMF system.
(see Figure 2 below).
- Typical
plant performance is shown in Figure 3 below.
- Algae
removal rates across the treatment system have been
very high (up to 3 log removal) (see Figures 4 and
5 below).
- The
plant has been 'user friendly' to operate and requires
little fine adjustment to achieve the treated water
outcomes.
Figure
1: Turbidity Removal

Figure
2: Colour Removal

Table
3: Typical Plant Performance

4.0 OPERATIONAL
ISSUES
In
the sixteen month period the following operational issues
have been encountered
-
A Giardia count was detected in the treated water
during commissioning test work. Subsequent test work
by Coliban Water established Giardia counts in the
Trentham raw water.
-
Algae removal across the CMF system in isolation has
not been measured at > 4 log as expected.
- Algae
counts have been experienced in pipework downstream
of the CMF plant.
- Algae
counts have increased across the GAC filter indicating
some growth in the vessel.
- A
membrane failure was experienced after a period of
six months resulting in the changeout of a membrane
set.
- Backwash
water has been above the criteria for return to the
reservoir.
4.1 Giardia
Issue
The
treated water count of Giardia was traced to using raw
water to commission the activated carbon vessel. Due
to the tight project program the CMF plant was commissioned
last so that microfiltered water was not available.
GAC needs to be thoroughly backwashed prior to service
to remove carbon fines. The Giardia was held in the
GAC filter and then subsequently carried through into
the treated water during commissioning.
The
carbon filter was backwashed for several hours with
a maximum dose of ozone. Subsequent testing of the treated
water showed no further sign of Giardia. Over the 16
month operation period the treated water has been routinely
tested for Giardia with none being detected.
In
hindsight the issue could have been averted in a couple
of ways,
-
Prior knowledge that the raw water contained Giardia.
Until
Giardia testing was done as part of the plant's performance
criteria, Coliban Water was not aware that the reservoirs
contained the cyst species. Awareness of such a factor
would have alerted commissioning engineers to not use
raw water in backwashing the carbon filter.
-
Installation of the CMF unit earlier could have provided
microfiltered, and therefore cyst free, water for
commissioning ozone and activated carbon filters.
4.2
Algae Issue
As
can be seen from Figure 4 below the count of algae in
the raw water reservoirs are extremely high over the
spring and summer period. This algae has been responsible
historically for the taste and odour issues in the Trentham
water supply.
Reservoir 2 has had the highest algae counts over the
period of the plant's operation. Coliban Water have
elected to draw raw water primarily from Reservoir 1
to keep the algae load on the treatment plant as low
as possible.
Figure
4 : Algae Counts in Raw
and Treated Water

Figure
5 below shows the log removal rating of algae across
the treatment system versus the incoming algae count.
The higher the incoming algae count the greater is the
log removal - approaching 3 log at counts of 22,000
per ml. At lower raw water algae levels the removal
rating is much less. This outcome is unexpected with
CMF as the first part of the treatment stage.
If we look at the data in Table 4 below an interesting
outcome is shown across the treatment process units.
The CMF plant is removing algae to very low levels but
levels post membrane filtration increase. This is evident
in the pipework immediately prior to the activated carbon
vessel and in water after the carbon. The only conclusion
that can be drawn from this data is that the algae is
breeding in the pipework and activated carbon vessel.
It
was discovered that the fibreglass vessel containing
the carbon was partially transparent to light. It has
now been painted to inhibit light. Further results from
January to June this year (Table 4) indicate algae levels
have fallen in the raw and treated water.
-
The apparent ability of algae to breed in pipework
and the activated carbon vessel was unexpected. Painting
of the carbon vessel has appeared to alleviate the
issue to some extent. Algae increases in pipework
(presumably dark) post membrane filtration is not
expected.
-
The actual algae counts are still very low in the
treated water to Trentham and no taste and odour issues
have been encountered over the spring and summer period.
- The
ability of the carbon filter to behave in a biological
manner (BOC) is certainly accounting for some of the
removal of the naturally occurring organic carbon.
This is evidenced by the removal of true colour across
the treatment system.
Figure
5: Log removal of Algae across the Treatment System

Table
4 : Algae Counts Across
the Treatment System

4.4 Membrane
Failure Issue
After
some six months of operation, routine integrity testing
of the membranes by 'air pressure decay' indicated loss
of integrity in the membrane bank.
Modules
were removed from the plant and tested in USF Australia's
laboratories. The membrane fibres were found to have
circular holes penetrating the wall. These holes were
some 5 to 40 micron in diameter - much larger than the
0.2 micron average pore size.
The
entire membrane bank was replaced under warranty by
USF.
The
exact cause of the holes in the membrane wall is still
not certain. Two possible explanations are:
-
The holes may have been caused by a membrane extrusion
manufacturing fault.
- The
holes may have been caused by some unknown material
in the raw water impinging on the membrane surface.
USF's
research and development team have concluded that the
failure was extremely rare and unlikely to occur again.
The current set of membranes have now been in operation
for 10 months and show no sign of loss of integrity.
4.5
Backwash Water Issue
Table
5 below shows testwork carried out on the backwash return
water from the settling lagoons. The backwash water
comes from the CMF plant and Activated Carbon Vessel
and returns to the source reservoirs via two simple
lagoons in parallel. Some natural settling taking place
in these lagoons.
The
quality of the backwash water in respect to Colour and
Turbidity is higher than normally permitted in a chemically
coagulated conventional treatment plant designs. Because
the Trentham plant is not dosing chemical coagulants,
the backwash water will not settle. There is concern
that, over time , this material returning to the raw
water reservoirs will impact on the treatment process.
The
issue can be resolved quite readily by introducing chemical
coagulation to settle the backwash water. This is not
seen as a desirable as the plant currently has no need
to introduce these chemicals.
Coliban Water and USF Australia propose to address this
issue by introducing a more passive 'root zone' wetland
approach in the settling lagoons. The proposed reed
beds will promote solids capture and biological removal
of the organics in the backwash water. This will hopefully
continue the 'non chemical' approach that the Trentham
WTP is demonstrating.
Table
5 : Backwash Water Return

5.0 CONCLUSION
Experience
with no-coagulation operation highlights some significant
advantages compared to treatment using chemical coagulation.
-
The process does not have to be finely tuned. There
is no dosing to be adjusted either for coagulation
or pH reduction. Changes in the solids content of
the raw water is automatically accommodated by the
microfiltration unit and it backwashing frequency.
The ozone system can operate under automatic redox
control ensuring maintenance of a small ozone residual
on the contact tank outlet even under varying raw
water conditions. With these two reliable steps ahead
of the GAC, the efficiency of its adsorption and biological
functions are unaffected.
- The
process is easier to control. As a result of the above
features, control of the plant is particularly straight
forward. There is no drop off in treated water quality
under stop/start conditions or when changes occur
in raw water quality.
-
Less chemical handling issues. There is a limited
reliance on chemicals so chemical inventory levels
do not need careful monitoring, and chemical storage
and delivery requirements are minimised.
-
Less sludge protection. No coagulant sludges are produced.
The only solids in the wastes generated are those
present in the raw water, and pH adjustment is not
required prior to return of settled washwater to the
source reservoirs.
The
operational issues experienced have highlighted the
following areas that need further work and understanding
at Trentham,
-
Algae activity in pipework and Activated Carbon Vessel
-
Backwash water handling in the absence of chemical
coagulants
The successful implementation and operation of the Trentham
WTP utilising a unique three step process of microfiltration,
ozonation and GAC/BAC filtration has demonstrated that
high quality treated water can be produced without chemical
coagulants under appropriate conditions.
The
application of this no-coagulant process on other Australian
waters may be particularly advantageous under the following
water quality conditions:
-
presence of giardia/cryptosporidium
- presence
of tastes and odours
- presence
of algal toxins
- low
to moderate algal mass
- low
to moderate true colour
6.0
AUTHORS
Michael
Muntisov is GHD's National Manager for Water Quality
and Treatment based in Melbourne, Jenny Stewart is a
Project Manager with Coliban Water and Colin Nash is
the Project Sales Manager with USF Australia. DOWNLOAD
(pdf
49K)
|