NATIMUK POTABLE WATER SUPPLY: LATERAL THINKING AND OPERATOR INPUT EQUALS $4M SAVED

Bert Pynappels, Works Coordinator, Service Delivery Group, GWMWater
Graeme Bartle-Smith, Strategic Project Engineer, GWMWater

pdfDOWNLOAD FULL PAPER (pdf 957 kb)

 

ABSTRACT

The Wimmera Mallee Pipeline Project was required to deliver piped raw water to supply the township of Natimuk. GWMWater planned to build a treatment plant in 2012. Innovative thinking by the design team identified options to bring drinking quality water from Horsham,
eliminating the need for a treatment plant and generating savings of nearly $4 M. As the design proceeded, further improvements meant that Natimuk could be supplied under gravity from Horsham’s treatment plant. The final design proved to have significant benefits for Horsham as well.


 

 