|
Conference Papers | 2004 Victorian Conference Papers
WEST
WODONGA BNR WASTEWATER TREATMENT PLANT UPGRADE
Peter
Tolsher,
Operations Manager, Purac
DOWNLOAD
(pdf
110 KB)
ABSTRACT
Two
major wastewater treatment plants, the Howard Street
Treatment Plant and West Wodonga BNR Plant, previously
serviced the township of Wodonga. West Wodonga BNR Plant
treated the entire industrial load and approximately
a quarter of the domestic load generated by the township
of Wodonga. Howard Street Treatment Plant, an older
trickling filter secondary standard plant located within
the township itself, treated the rest of the domestic
load. For various reasons a decision was made to close
down the Howard St plant and divert all flows to West
Wodonga.
This
paper describes the history & background, the selection
process - Authority's expectations of an operating company,
combining the old plant with the new, commissioning
- hazop with site operators, introducing a site specific
quality system, plant commissioning and why partnerships?
It also describes the plant upgrade by PURAC in 2002/3
to provide advanced secondary treatment by Biological
Nutrient Removal (BNR) process followed by UV disinfection.
The plant also includes an advanced treatment process
for production of high quality reclaimed effluent for
re-use on and off site.
KEY
WORDS
Biological
nutrient removal (BNR), Tertiary treatment, Partnerships,
Bardenpho, North East Water (NEW) Design, Build, Operate
(DBO)
1.0
INTRODUCTION
North
East Water had two treatment plants which serviced the
township on Wodonga, Howard Street and West Wodonga.
Howard Street was a trickle filter plant, in the town
limits which didn't meet the new EPA discharge requirements,
so the decision was to close it down and send all flows
to West Wodonga plant. To do this the West Wodonga plant
had to be upgraded to cope with the increased flow and
loads.
The
nominal capacity of the West Wodonga BNR plant was exceeded
under existing loading conditions and with the continued
tightening of EPA requirements on effluent quality and
the increased load expected from Howard St Plant before
2001, a significant upgrade of the West Wodonga Plant
was required immediately.
1.1
History of The West Wodonga Purification Plant (WWPP)
This
plant is located on Old Barnawartha Road, Wodonga West.
Stages 1 and 2 consisting of an oxidation ditch were
commissioned in 1986. During 1989, Stage 3 was constructed,
adding biological nutrient removal facilities. Stages
4A and 4B were implemented during 1992 to 1994. This
involved augmentation of the aeration capacity, modification
of the BNR process to the University of Cape Town process,
addition of chemical dosing facilities and construction
of 2 additional clarifiers.
After
completion of stage 4B in 1994 the plant had a capacity
of about 81,000 equivalent population (EP) on a biochemical
oxygen demand (BOD basis).
In
2002/3 the plant was upgraded by PURAC to provide advanced
secondary treatment by Biological Nutrient Removal (BNR)
using a 5 stage Bardenpho, process followed by UV disinfection.
The upgraded plant has a capacity of around 130 000
EP on a BOD basis.
1.2
Why Partnership
North
East Water wanted a large international water company
to design, build and operate the plant in partnership
with them so that the expertise that a large company
has, could enhance NEW's total business performance
over the contract term. This operating period of ten
years plus the option of a further 5 years plus another
5 years on agreement was preferred to give the private
company the incentive to provide a quality plant that
would operate reliably in the long term. This, for example,
resulted in selection of good quality mechanical plant
that had proven local support.
There
is also the opportunity to share the risk associated
with the design, construction and operations of the
upgraded plant and efficiency sharing with other treatment
processes within the water authority. The partnership
was also favoured by the Victorian Government as it
puts the large commercial business in to the local water
environment. The Design, Build and Operate (DBO) framework
has similarities with BOOT schemes except that in DBO
project the water authority funds and retains ownership
of the capital works when they are completed.
1.3
The Selection Process
North
East Water called for expression of interest to design
build and operate the brown field West Wodonga Waste
Water Treatment Plant. There were 14 interested parties
that were short listed to 4 (prior to the Tender period)
based on the information provided in their submissions,
also the expertise of each party and the concept solution
put forward. North East Water management and operators
went and visited other authorities and councils that
had dealt with the companies on the short list to find
out back ground information so they could make the right
decision. The four short listed parties were invited
to submit a tender for the project. Three tenders were
received by NEW and evaluated in accordance with predefined
criteria. After the long arduous process Purac won the
contract to design, build and operate the plant. Robert
Proctor was the engineer who designed the plant. His
expertise and ability to take on board the site operators
comments has made it an operator friendly plant with
quality effluent that meets the licence.
1.4
Combining the Old with the New
The
plant upgrade was designed to utilize the existing plant
and to continue to operate while the construction of
the plant was in progress. This was done in conjunction
with the site operators at planned site meetings on
a daily basis. The input into the plant operations to
make it an operator friendly plant was taken on board
even as the plant was being built by the construction
staff.
1.5
Commissioning
The
upgrade was commissioned in early 2003. The commissioning
process went smoothly helped by use of detailed procedures
for each section of the plant. It was also helped by
having already thoroughly tested the new PLC/SCADA control
system off site.
Operating
the plant through the commissioning process was the
best way to learn how the new systems all worked. As
Operations Manager I had a key role, and was given the
ultimate responsibility for approving when and how commissioning
activities would be carried out that affected the operation
of the existing plant. One example of this was bringing
the new bioreactor on line, as we had to build up activated
sludge in the existing bioreactor and then split the
sludge between the new and old bioreactors.
1.6
From a Water Authority to Private Company
The
transfer from the water authority to the new private
company was something that could be considered as a
bold move after having spent 18 years at the authority.
The contract was written so that the operators of the
site had the option to be seconded to Purac or be relocated
to a new site within the water authority.
After
a lot of discussions with the Managers of North East
Water & Purac, two of us decided to transfer across.
This is a decision that I don't regret as it was a great
way of learning the way a private company operates.
We went from general operating of the plant to setting
up site specific Quality & OH&S systems, setting
up a new control room, office, visitors centre, setting
up budgets and having input into the design and construction
phase.
As
Purac operates other plants in Redcliffe Qld and Wellington
in New Zealand I have had the opportunity to visit these
plants and now have been appointed the operations manager
of the Redcliffe plant.
2.0
THE UPGRADED TREATMENT PROCESS
2.1
Wastewater Characteristics
The
upgraded West Wodonga plant receives 11 ML/d on average
of wastewater made up of domestic and industrial components.
COD load ranges from 10 000 to 18 000 kg/d. A big challenge
for plant operation is that around 75% of the total
COD load is from a pet food factory and an abattoir.
This makes the wastewater very variable in strength
depending on their production cycles.
2.2
Inlet Works (Pre Treatment)
The
inlet works was retrofitted to cope with the increased
flow and now includes new items of:
- Variable
speed Flygt N series inlet lift pumps;
- 2
auto step screens, screen bypass channel, vortex grit
removal chamber, screening washing and compaction
system, grit washing system, grit and screening skip
collection system.
2.3
Odour Control System
The
Inlet Works has been identified as the only area that
generates significant odours (typically hydrogen sulphide
and methyl mercaptan). Close fitting covers have been
installed over the various odourous areas and foul air
blowers draw controlled amounts of air to the Odour
Control System via ductwork.
The
Odour Control System is a fully self controlled, two
stage system comprising Biofilter and Activated Carbon
technology. An exhaust stack and all associated instruments
and controls are included.
2.4
Bio Reactors
The
old Bioreactor was upgraded with new mixers and replacement
diffuser membranes. There was also a need for a second
new Bioreactor to be provided in parallel. Flow is split
approximately evenly between the two bioreactors. The
bioreactors are designed to provide biological nitrogen
and phosphorous removal using a five-stage Bardenpho
configuration, which comprises two anaerobic zones,
two anoxic zones, two aerobic zones, a post anoxic zone
and a post aerobic zone.
The
new bioreactor is designed to form a fully integrated
process with the old bioreactor. Rather than being based
on an oxidation ditch race course configuration it contains
segmented anaerobic, anoxic and aerobic zones.
2.5
Aeration System Upgrade
The
existing oxidation ditch is supplied with air by two
duty multi stage blowers with a third blower as a standby
unit. There was also further air transferred into the
existing ditch by four horizontal brush aerators that
also provide circulation of the mixed liquor. The gearbox
drives were at the end of their life so two were decommissioned
and two Flygt banana mixers were installed in their
place to improve the oxidation ditch circulation.
Three
new positive displacement blowers (two duty and one
standby) were installed to service the new Bioreactor
and Aerobic Digesters.
2.6
Clarifiers
Provision
of the additional bioreactor volume enabled mixed liquor
levels to be reduced so that the three existing clarifiers
could service the increased plant load and throughput.
Clarifier 1 was fitted with a sludge blanket level detection
to monitor for potential settling problems, enabling
timely rectification.
2.7
UV System and Outfall
All
flows to the river are disinfected by a Wedeco UV system,
prior to discharging through the outfall to the Murray
River. The outfall capacity is up to 15 ML/d under gravity
and up to 20 ML/d using booster pumping. Higher flows
are diverted to and stored temporarily in a purpose
built flow equalisation facility.
The
UV system treats all flows to the river. The system
has a capacity of 20 ML/d of secondary treated sewage.
Instantaneous flows in excess of 20 ML/d are directed
to the Flow Balancing Basin via an automated overflow
weir system at the UV inlet.
The
Wedeco UV system features high output, low pressure
lamps which achieve high power efficiency and low fouling
and compact units. Lamp power is automatically varied
to suit flow rate and measured (on-line) UV intensity.
The system also includes in-situ automatic cleaning.
All
treated effluent is monitored by a Greenspan online
analyser for Phosphorus, Ammonia, pH and nitrate which
is sent back to the citec programme.
Table
1: Effluent Discharge Data for month of May 2004

2.8
Sand Filtration for Offsite & Onsite Reuse
Deep
bed sand filtration is provided by a system of modular
continuous backwashing filters (Dynasand). The Dynasand
system provides continuous filtration through a deep
sand bed that is continuously being circulated and washed
(by an air lift pump system). This means separate backwash
pumps and clean/dirty water storage tanks are not required.
The
Dynasand system is well proven in tertiary treatment
applications and has the advantage of high solids handling/removal
capability.
The
filter influent is pumped to the filters from the UV
channel inlet chamber and dosed with alum to assist
coagulation/filtration the filtrate then gravitates
to a chlorine contact tank system. The dirty water from
filter washing flows by gravity back to the biological
process. As the Dynasand system is modular, it is relatively
simple to install new parallel units to increase re-use
treatment capacity in the future.
The
Dynasand system provides up to 60L/s of treated water
for on and off-site re-use. Off-site reuse is sent to
the golf course, Latrobe University, Tafe and Victory
Primary School on a pressurised demand system.
2.9
Chlorine Contact
A
30 min HRT chlorine contact tank system is provided
downstream of the filters. The feed is dosed with gaseous
chlorine, to achieve a chlorine residual value as measured
by an on-line analyser. The treated water is then pumped
to the re-use main by 2 x 50% duty pumps.
The
treated water quality is continuously measured by turbidity
and chlorine residual online analysers.
2.10
Sludge Wasting and Thickening
Sludge
is wasted as mixed liquor and thickened in a DAF unit
to achieve a solids concentration of around 4% for feeding
to the Aerobic Digesters. The dewatering centrifuge
can be used as a backup thickening unit. The thickened
sludge is pumped directly to the Digesters by helical
rotor pumps.
2.11
Aerobic Digesters
Two
digesters are provided, giving a solid retention time
of 30 days. This, combined with the sludge age in the
Bioreactors, gives a total age of 40 days, which is
enough to ensure achievement of EPA Class B (T3) stability
criteria.
The
digesters are fed directly from either the DAF thickener
or the centrifuge. The digesters are aerated by a diffused
air system, fed by the same blowers as the new Bioreactor
2. The digesters are aerated on an intermittent basis
in order to denitrify and therefore minimise return
of nitrogen with the dewatering liquors to the Bioreactors.
As the digesters are aerobic, the release of phosphorous
is reduced. However, to ensure no adverse peaks are
applied to the Bioreactors, alum dosing is also provided
to the dewatering return liquor system which goes back
to the inlet works to go through the process.
2.12
Sludge Dewatering and Drying
The
digested sludge is dewatered by a new G-tech centrifuge,
with the existing Tema belt press used as a standby
facility. The combination of upstream sludge thickening/digestion
centrifuge dewatering enables a dewatered sludge of
around 15 to 20% solids level to be achieved.
The dewatered cake will then be dried out further to
approximately 60% in a sludge drying facility which
is still under construction. The area will have clay
lining to minimise leaching and a drainage collection/return
system. Biosolids will be stored on site for a maximum
of 12 months until it is taken off site for agricultural
reuse to farmland.
2.13
Control System
The
upgraded plant has a comprehensive automatic monitoring
and control system. Advanced on-line monitoring is provided
including effluent nitrate, ammonia, phosphate and pH.
Critical
alarms are sent as text messages to mobile phones carried
by the operators and each operator has their own notebook
computer enabling them to remotely dial into the full
control system.
3.0 CONCLUSION
After
the augmentation has been completed, there is extra
flexibility built into the plant and we have better
control of the process in order to aid nutrient removal.
This will mean more consistent compliance with our EPA
discharge licence.
The
transfer to the private sector has been a rewarding
experience with a steep learning curve that I would
not change. There are more opportunities with the new
company for learning technology from the experienced
staff they have and it has been a rewarding career move.
DOWNLOAD
(pdf
110 KB)
|