|
Conference Papers | 2003 Conference Papers
AERATION
SYSTEMS - DIFFUSED CHAOS OR CONTROLLED BOILING
Michael
Naughton,
Superintendent Black Rock STP, Barwon
Water
DOWNLOAD
(pdf
824KB)
ABSTRACT
The
paper describes the aeration system at the Black Rock
Sewage Treatment Plant and discusses the methods adopted
to effectively manage, maintain and replace the 42,000
fine bubble diffusers used to aerate the plant.
The
objective of the work on the aeration system and diffusers
at the plant is to maximise the life of the diffusers,
minimise the energy used in the plant while providing
optimum process performance.
The
centrifugal compressors and diffused air distribution
system are the heart and veins through which the lifeblood
of the plant flows. The flow of air provides the oxygen
which keeps aerobic micro-organisms alive and well in
the Intermittently Decanted Extended Aeration (IDEA)
plant.
KEYWORDS
Sewage
treatment, IDEA, fine bubble diffusers, cleaning program,
diffuser replacement program.
1.0
INTRODUCTION
Without an effective method of record keeping to track
the history of maintenance and performance on each of
the diffuser manifolds at the Black Rock Sewage Treatment
Plant, decision making on when to replace the diffusers
is at best just a stab in the dark. Decisions based
on "those stabs in the dark" would have been
very costly and contributed to a significant downturn
in performance.
The
Black Rock Sewage Treatment Plant south of Geelong in
Victoria was upgraded in 1996 to Secondary Treatment
utilising the IDEA process. The $46 Million upgrade
established the plant as the largest of its type in
the southern hemisphere at the time. The Black Rock
plant receives wastewater from the Greater Geelong area
extending from Lara in the north, east to Queenscliff
and south to Torquay/Jan Juc with an equivalent population
of approximately 200,000.
The
plant has a design average dry weather flow capacity
of 70 ML/day with a peak wet weather flow capacity of
210 ML/day. The plant has a minimum hydraulic retention
time of 32 hours and operates with a sludge age of approximately
30 days. It treats effluent from domestic and industrial
sources with an average biochemical oxygen demand (BOD)
of 370 mg/L and suspended solids (SS) of 360 mg/L to
produce an effluent consistently below 10 mg/L BOD and
10 mg/L SS.
The
process uses two selector tanks that feed four aeration
tanks with continuous inflow. The process is based around
a four hour cycle that aerates for 2 hours settles for
1 hour and decants during the last hour. The aeration
system consists of 3x750 kW Centrifugal Compressors
that provide air to the 42,000 fine bubble diffusers
mounted on 640 stainless steel manifolds. The manifolds
are 12 metres long and 3.5 metres wide. Each manifold
has 64 ethylene propylene diene monomer (EPDM) diffusers
fitted. The aeration system in operation in Tank 4 is
shown in Figure 1.
Figure
1: Aeration System in Operation

2.0
DISCUSSION
The
Operations and Maintenance manuals provided by Contractors
following the construction of new works at any modern
treatment facility contain much valuable information.
However, there are many issues that are not included.
One
basic piece of information not generally referred to
is that of record keeping. It is fair to say that any
reasonable operator would be expected to keep appropriate
records. However, when you have a diffused air distribution
system in four aeration tanks that has a total of 42,000
fine bubble diffusers it can be a major exercise to
keep those records. So, how much detail is enough and
what use can those records be?
Since
the plant was constructed there have been a number of
developments made possible in part because of the quality
of the records kept. It was identified very early in
the life of the IDEA plant that the operation and maintenance
of the aeration system would be of major importance
to not only the biological treatment process but to
the efficiency and cost of running the plant.
Because
it is possible to isolate and lift individual manifolds
from each tank (while keeping the tank online), actions
to clean or replace diffusers are usually carried out
on all diffusers mounted on the manifold at the time
of removal. Therefore it was considered unnecessary
to keep records on the individual diffusers.
A
record is kept of the maintenance history of each individual
manifold. A coding system was developed to identify
individual manifold locations and their history of maintenance.
Microsoft Excel was chosen as a program suited to recording
those details, which most plant staff could utilise
without specialist training. The spreadsheet is formatted
to reflect the actual manifold position in the tank.
A typical maintenance record is shown in Figure 2.
Figure
2: Part of a typical maintenance record

The recording system allows operations staff to determine:
- The
manifold position within the tank and cell;
- The
manifold identification plate number;
- The
type of diffuser installed;
- When
the diffuser was installed;
- When
the diffuser was cleaned;
- Whether
diffusers have failed;
- If
there has been any history of corrosion and repairs;
- Where
testing and dosing connection points have been fitted.
Analysis
of the records together with other performance data
collected have become a valuable tool in assisting to:
- Establish
an effective replacement program for the diffusers.
- Determine
an efficient cleaning program to extend the effective
life of the diffusers.
- Maintain
effective and efficient process performance.
- Develop
budgets for costs to clean and replace diffusers.
3.0
REPLACEMENT PROGRAM
As
a result of issues that arose during construction of
the plant, it was considered prudent to take a conservative
approach in establishing a suitable diffuser replacement
program.
3.1
Working Life
The
working life of new EPDM diffusers was expected to be
between 4 to 6 years largely depending on the characteristics
of the wastewater entering the aeration tanks. The wastewater
flow entering the plant is made up of 85% domestic flow
with 15% from industrial sources. This type of reasonably
aggressive influent had the potential to adversely effect
the life of the diffusers. A number of splits in the
diffuser membranes were apparent in the first 12 months
following commissioning which added further to the uncertainty
of the working life. This appears, however, to have
been the result of the construction process.
3.2
Supply of Replacement Membranes
As
the plant uses some 42,000 diffusers a further consideration
in the replacement program is the ability to source,
transport and physically replace that number of units.
If it was proposed to wait until it was apparent that
the diffusers had reached the end of their working life,
then it must be recognised that it can take up to 6
months to have the membranes manufactured and delivered.
3.3
Diffuser Reconditioning
Several
aspects have to be considered in the method of replacing
diffusers. Initially, a decision has to be made as to
whether to replace the membranes only or to replace
the entire diffuser. As the membranes generally seemed
to be the only component that had deteriorated in condition
it was decided to replace only the membrane. This results
in a net saving of about $5 per unit over replacing
the entire diffuser. Where other components were found
to be faulty they were replaced.
The
reconditioning of 10,000 diffusers takes about 1 month
to complete using specialist contractors. It is crucial
to the process that the diffusers are very carefully
checked for defects before leaving the factory and once
again immediately prior to fitting. This level of checking
is necessary to avoid fitting any diffusers with faults.
If
faulty diffusers are installed it generally leads to
the manifold and all of its diffusers filling with sludge.
This results in having to remove the manifold from the
tank, draining the manifold of sludge, removing and
replacing each diffuser and then stripping, washing
and rebuilding each of the flooded diffusers.
3.4
Method of Replacement
Originally
it was felt that the best way to replace each diffuser
was to isolate and drain each tank. The tank and diffused
air equipment would be washed down and then each diffuser
would be replaced. However it was difficult to quantify
the time necessary to adequately clean down the tank.
The tank has a flat floor with only one sump. Combined
with a concrete inlet tunnel mounted on the floor dividing
the tank, it was likely to be a time consuming task
to clean out the tank thoroughly.
Any
delays caused through either Occupational Health and
Safety (OH&S) issues or industrial relations problems
with the large labour force required would also have
the effect of increasing costs considerably.
The
alternative method of replacing the diffusers was to
keep the tank online and remove each manifold one at
a time. This has some clear operational and cost advantages
over the first method considered. The cost of this method
is approximately 40% of the alternative.
The Gantry Crane and rail system (see Figure 3) traverses
the entire area of each of the four aeration tanks readily
allowing isolation and removal of each of the manifolds
individually.
Figure
3: Gantry Crane and rail system

This
method also allows a more thorough inspection of the
manifold condition and diffusers. The aeration tank
stays online and does not have to be cleaned and desludged.
Work is carried out by two persons who are also able
to repair any areas of corrosion that are found. To
date very few manifolds have required repair. As each
diffuser was replaced the rubber "O" ring
sealing the diffuser against the manifold was also replaced.
Due
to the relatively long lead time required to carry out
a diffuser replacement program and the significant number
of membrane defects identified during commissioning
and immediately after it was considered appropriate
stagger or spread the replacement program over a number
of years. It was also decided to adopt a fairly conservative
working life of 4-5 years for the original diffusers.
This allowed the program to be spread over a period
of at least 4 years.
Figure
4: Schedule of Work

4.0
CLEANING PROGRAM
Having
adopted a fairly conservative program initially it was
very important to establish the actual maximum working
life of the diffusers as soon as possible. This also
meant investigating methods to extend the working life
of the diffusers. To make decisions toward this goal
it was necessary to find ways to measure and record
the performance of the diffusers.
Originally
it was thought that the main cause for the deterioration
in diffuser performance was that of the EPDM material
becoming brittle and thereby increasing diffuser backpressure.
However, while examining the function of increasing
backpressure it was identified that the growth of a
biofilm over the membrane was also contributing to the
increase in backpressure.
4.1
Measuring Performance
Aqua-Audit
was contracted to assist with the measurement of diffuser
performance. Tom Lawson from Aqua-Audits has had a long
involvement in the development of diffusers in Australia
and has developed a number of methods to measure diffuser
performance. Barwon Water purchased monitoring equipment,
which allows plant staff to carry out the performance
testing inhouse.
A
monitoring program was established to measure backpressure
across the diffuser membranes. This allows the increase
in backpressure to be monitored over time. It has also
enabled the point where it is necessary to act to improve
the diffuser membrane performance to be determined.
This point is a backpressure around 13 kPa. A sample
of the results of the testing is shown in Figure 5.
Figure
5: Typical Plot of Diffuser Backpressure against Flow

Several
trials were carried out to determine the improvement
in performance that could be gained by cleaning the
membranes. A range of high-pressure cleaners was used
with hot and cold water together with a number of different
cleaning chemicals. Visual inspections showed that cleaning
the diffusers produced a considerable improvement in
aeration performance.
A
cleaning program was commenced while further measurements
were taken to quantify the improvement. Figure 6 shows
the cleaning operation.
Figure 6: Diffuser cleaning

Results
show that following cleaning the diffusers return to
a state similar to that when new (approximately 5-6
kPa.). A graph of the decrease in backpressure achieved
through cleaning is shown in Figure 7.
Figure
7: Typical diffuser backpressure before and after cleaning
It
has been established that the diffusers should be cleaned
every two years to ensure optimum efficiency. Better
cleaning techniques are being developed to try to resist
the growth of the biofilm and prevent damage to the
membrane during cleaning. One version of the diffusers
supplied has sustained minor damage as a result of using
an aggressive approach to the cleaning.
A
cleaning procedure has been developed to prevent damage
during cleaning whilst retaining maximum benefit from
the operation.
4.2
Further Challenges
The
maintenance program is being continually developed to
take advantage of improvements in diffuser technology
and to prolong the life of the membranes through better
cleaning techniques. Investigations are also underway
in the use of chemicals to resist growth of biofilms
on the diffuser membranes.
A
number of tests on the use of formic acid dosing through
the aeration system to clean the membranes have also
been carried out. It remains to be seen whether the
effect of this type of cleaning can match that of the
current methods adopted. The performance of other diffusers
in the market place also needs to be evaluated. A number
of alternative types of diffusers are currently being
trialed.
The
effect of diffuser condition on energy efficiencies
is also being monitored. The costs associated with the
operation and maintenance of the aeration system at
the plant make up a significant component of the plant
budget. The aeration system directly affects the amount
of power used at the plant, which is also a large part
of the budget. The value of the developments mentioned
should not be underestimated.
The
program has been developed from the initial diffuser
replacement frequency of 4 years to the point where
diffuser replacement is now every 6 years. It is likely
that the working life of the diffusers will be extended
to 7 years in the near future. The annual costs of the
diffuser maintenance and replacement to date have been
reduced by $175,000.
5.0
CONCLUSIONS
A
number of advances in the way the Operations Staff at
the Black Rock Plant maintain and operate the Aeration
Distribution System have been explained. However it
must be acknowledged that few of the advances made to
date would not have been possible without the establishment
of an accurate and concise recording system.
The
accuracy and completeness of the records relies on the
cooperation and dedication of the contractors and plant
staff. The Black Rock Plant has always had people prepared
to commit to the system. As a result it can be demonstrated
that plant efficiencies have increased and budgets decreased.
It is clear that it is not a state of "diffused
chaos" but one of "controlled boiling".
6.0
ACKNOWLEDGEMENTS
The
assistance of the following people is greatly appreciated:
- Mr. Tom Lawson (Aqua-Audit)
-
Mr. Lincoln Thomson (Barwon Water)
- Mr. David Barkley (Barwon Water)
- Mr. Tyler Dutton (Barwon Water)
7.0
REFERENCES
Aqua
- Audit (2000), Black Rock WWTP, Diffused Air Aeration
System, Report on Diffuser Pressure Loss Characteristics
DOWNLOAD
(pdf
824KB)
|