|
Conference Papers | 2002 Conference Papers PROCESS
OPTIMISATION OF AN UPFLOW SLUDGE BLANKET CLARIFIER THROUGH
THE INSTALLATION OF TUBE SETTLERS
Shaun Cumming, Operations
Coordinator,
Barwon Region Water Authority
DOWNLOAD
(pdf
736KB)
ABSTRACT
Flocculation
and clarification at the Airey's Inlet Water Treatment
Plant is achieved via an upflow sludge blanket clarifier.
Raw water characteristics and the mode of plant operation
made it difficult to achieve acceptable sediment removal
through the clarifier. High solids loadings on downstream
filters resulted.
In
October 2001 tube settlers were installed to optimise
clarifier performance. The result was a significant
improvement in clarifier performance and, in turn, treated
water quality. Theoretical calculations of tube settler
performance correlate well to the actual performance
of the clarifier.
KEY WORDS
Upflow sludge blanket clarifier, tube settlers, process
optimisation.
1.0
INTRODUCTION
The Aireys Inlet Water Treatment Plant (AIWTP) is a
2 ML/day plant, commissioned in 1991 and consisting
of:-
-
Pre-oxidation (Sodium Hypochlorite addition);
- Flocculation
and Clarification (Upflow sludge blanket clarifier
using Aluminium Sulphate as a coagulant, polymer as
a flocculation aid and Soda Ash for pH correction);
- Filtration
(Closed gravity sand filters);
- Disinfection
(Sodium Hypochlorite addition) and pH Correction (Soda
Ash addition); and
- Clear
Water Storage (2.4ML covered basin).
Raw water is sourced from the Painkalac Creek, which
is high in colour, organic content and turbidity. Typically
the raw water has a colour between 300-500 Pt/Co, UV
254 Absorbance between 0.6 and 0.9 units/cm and Turbidity
between 14 and 35 NTU.
The
key process element of the Airey's Inlet treatment train
is the upflow sludge blanket clarifier. Sludge blanket
clarifiers incorporate both flocculation and sedimentation
in one unit. Chemically dosed water enters a central
delay/distribution chamber where mixing and initial
floc formation occurs. Flow is then distributed across
the bottom of the clarifier through distribution arms.
Launders collect clarified water at the top of the clarifier.
Turbulence
produced by the water inflow promotes flocculation in
the lower zone of the clarifier. As solids accumulate
a suspended sludge layer (blanket) forms. Clarification
is achieved through agglomeration within the blanket
and by maintaining an upflow velocity less than the
settling velocity of the floc particles.
Figure
1: Upflow Sludge Blanket Clarifier

The performance of the Airey's Inlet upflow sludge blanket
clarifier was compromised by:-
-
Intermittent operation of the plant. During winter
months plant operations are reduced to two twelve-hour
runs a week. Sludge blanket units perform best under
continuous and constant flow conditions;
- Hydraulic
shock loading of the clarifier on plant start-up,
due to the on/off operation of the inflow pumps;
- Uneven
inflow distribution and temperature gradients within
the clarifier; and
- The
light nature of floc produced from the raw water.
The
result was floc carry over from the clarifier, placing
high loads on the filters and in turn affecting treated
water quality.
A
number of process optimisation options were investigated,
including AC Clarification, lower capacity inlet pumps,
variable speed drives and actuated valves on the inlet
pumps and installation of tube settlers. Tube settlers
were selected as the preferred option and installed
in October 2001.
2.0
DISCUSSION
The
amount of sediment removed by a clarifier is controlled
by the overflow rate (flow rate/surface area). Tube
settlers are used as a means of increasing the surface
area of a clarifier and, in turn, improving sediment
removal.
Tube settlers are a lightweight structure composed of
closely spaced tubes on an incline (usually between
40 and 60 degrees). Clarifier upflow is passed through
these tubes. Settling within these tubes and contact
clarification of fine floc results in a build-up of
particles on the tube surfaces. Particles combine to
form agglomerates which become heavy enough to slough
against the upward flow and slide down the tube slope
to join the sludge blanket below.
2.1
The Installation
Tube settlers for the Airey's Inlet clarifier were sourced
from Aquagenics Pty Ltd. They are supplied in module
form - each being 1 meter wide by 1 meter long by 0.67
meters high. The modules are arranged on a supporting
framework to form a layer within the clarifier. Figures
2 and 3 show the supporting framework, module installation
and settler positioning at Airey's Inlet.
Figures
2 and 3: Supporting Framework/Module Installation and
Settler Positioning


The supporting framework was designed by Barwon Water
and fabricated and installed by a local engineering
company. The framework is held up by a number of 'hooks'
over the top rim of the clarifier tank. This was done
to minimise the installation time. The entire installation
was completed in three days. The clear water storage
was filled to capacity prior to installation of the
tube settlers to allow for the three days the plant
was off line. If required the plant could have been
brought back on line on the first day once the framework
was installed.
The
tube settlers are suspended at a height 700mm below
the top water level.
2.2 Operational Outcomes
A significant improvement in plant performance has been
achieved through the installation of tube settlers.
Graph 1 and table 1, compare typical plant runs pre
and post tube settler installation. In addition to improving
solids removal under stable operating conditions the
tube settlers have eliminated the sludge blanket carry
over that was previously evident for the first three
and a half hours of plant run.
In
conjunction with the increase in surface area brought
about by the tube settlers a number of other factors
contribute to the improved performance. These include:-
-
A distributing pressure loss created by the tube settlers
improves flow distribution and so improves clarifier
area utilisation;
- A
concentration of sludge particles occurs below the
tube settlers and acts as a secondary sludge blanket;
and
- The
tube settler layer reduces sunlight penetration into
the clarifier and therefore reduces the temperature
gradient across the clarifier height.
Graph
1: Clarified Water Turbidity Comparison

Table
1: Clarified Water Turbidity Comparison

Increasing the surface area means that plant flow rates
can be increased whilst still maintaining an acceptable
overflow rate. Previously, operating the plant above
25L/s resulted in significant carry over. With the tube
settlers installed good clarifier performance has been
achieved at flow rates as high as 33L/s.
This
means that in addition to water quality improvements
the tube settlers have provided a capacity upgrade.
The ability to run the plant at higher flows has reduced
the plant run time required which translates to operational
savings. The operation savings generated will see the
project pay for itself within an eighteen month period.
2.3
Theoretical Evaluation
The theoretical evaluation of the performance of the
tube settlers is provided in Figure 4.
Figure
4: Theoretical evaluation of the performance of the
tube settlers

In
order to relate the theory back to reality, i.e. the
actual operation of the Airey's Inlet clarifier, a settling
column analysis was conducted. Flocculated water was
placed in a column and mixed to achieve a uniform distribution
of particles at the beginning of the experiment. Samples
were then collected from ports at pre-determined time
intervals, and analysed for turbidity. The output of
the experiment is the settling curve for the floc particles
shown below.
Graph
2: Airey's Inlet Floc Particles Settling Curve

Removal ratios for given overflow rates (So) can be
estimated from the curve. Vertical lines have been drawn
on the graph at points corresponding to the Airey's
So values for pre and post tube settler installation.
The removal ratio is then estimated by drawing a horizontal
line between the 'vertical So line' and the y-axis at
a point where the area between the line and the settling
curve is equal both above and below the line. As marked
on graph 2 the removal ratio prior to tube settler installation
was 0.805. Installation of the tube settlers increased
this ratio to 0.86. The table below uses these removal
ratios to obtain an expected clarified water turbidity
pre and post tube settler installation.
Table
2: Theoretical v's Actual Turbidity Removal
The
results show a good correlation between theoretical
turbidity values and the actual operational results.
It
should be noted that the above calculations relate to
type I (Discrete) and type II (Flocculant) settling
only. That is, the zone above the sludge blanket.
3.0
CONCLUSION
In conclusion, a significant improvement in the performance
of the Airey's Inlet upflow sludge blanket clarifier
has resulted from the installation of tube settlers.
Clarified water turbidity levels under stable operating
conditions have dropped from 5NTU to 3.8NTU. The extended
period of blanket carry-over after plant start-up has
been eliminated bringing the average turbidity over
a run down from 8.5NTU to 3.22NTU.
The
improved performance is the result of a combination
of an increase in clarifier surface area, even distribution
of up-flows, formation of a secondary sludge blanket
and reduced temperature gradient.
On
a theoretical basis the tube settlers were found to
reduce the overflow rate by a factor of 6.75. Field
experiments showed a good correlation between the theoretical
analysis and the actual operating results. Settling
curve analysis can be used to provide a good indication
of tube settler performance.
In
addition to water quality improvements the tube settlers
have allowed the plant to be run at a flow rate 8L/s
faster than previous. This equates to an operational
saving that will see the project pay itself off within
18 months.
4.0
ACKNOWLEDGEMENTS
The assistance and support of the following people,
in the preparation of this paper, is greatly appreciated.
Mark
Dwyer, for the collation of operational and experimental
data and dedication to the efficient operation of the
Airey's Inlet Water Treatment Plant.
P.
Dharmabalan, for advice and guidance regarding theoretical
calculations.
5.0
REFERENCES
The
following resource was referenced in the development
of this paper:-
Deakin University Course Notes, SEV412 Environmental
Engineering Design 2, 1997. DOWNLOAD
(pdf
736KB)
|