|
Conference Papers | 2001 Conference Papers AIR
SCOURING OF WATER MAINS AN ASSET MANAGEMENT APPROACH
Peter Kitney -
Water Quality & Environmental Specialist,
Western Region Water Authority
Steve Codd -
GIS Coordinator,
Western Region Water Authority
Rick Woulfe
- Mains Cleaning Supervisor,
Western Region Water Authority
DOWNLOAD
(pdf
61K)
ABSTRACT
Mains
cleaning programs are now common practice in the water
industry to improve or maintain drinking water quality
to meet business plan targets, guideline requirements
and customer expectations. In addition to cleaning the
mains, a carefully planned program provides the additional
opportunity to collect important system asset information.
Western
Water commenced a systematic mains cleaning program
in year 2000 primarily using air scouring technique.
The mains cleaning program compliments a wide range
of treatment plant improvements completed over recent
years. The program is also driven by Western Waters'
strategic plan to control taste and odours throughout
the water supply system.
This
paper discusses:
| » |
issues
that lead to Western Water implementing a system
wide mains cleaning program; |
| » |
the
air scouring process; |
| » |
critical
operational and planning activities undertaken as
part of the mains cleaning program; and |
| » |
systems
developed to collect and digitise system asset information. |
KEYWORDS
Air scouring, GIS, Water Quality, Asset Management.
1.0 INTRODUCTION
The
primary objectives of supplying potable water to Western
Water customers is to ensure that the product is clear,
safe and pleasant to drink, meets appropriate drinking
water quality standards, delivers business plan targets
and the requirements of our Customer Charter.
Over
recent years many water quality improvement works have
been completed throughout Western Water's system to
meet these objectives. Completion of these programs
ensures that water supplied to the majority of our customers
is now filtered and disinfected.
The introduction of a largely filtered system over recent
years however does not totally eliminate sediments from
entering and settling within our water supply system.
Treatment
plant malfunctions allowing turbidity and microbiological
break through, burst mains, mains replacement works,
open service basins, seasonal flow / pressure variations,
deteriorating old mains, irregular tank cleaning programs
and poor mains system designs all contribute to sediment
build up, water discolouration and microbiological regrowth
within mains supply systems.
This situation presented the ongoing need for the introduction
of a system wide mains cleaning program. Western Water
commenced systematic mains cleaning program in 2000
primarily using air scouring technique, however in some
situations it was still recognised that flushing and
swabbing techniques were more suited.
The
objective of the mains cleaning program is to remove
a build up of sediment and biofilms in the system to
compliment a wide range of treatment plant improvements
completed over recent years.
The program is also driven by the company strategic
plan to control taste and odours throughout the water
supply system and reduce customer dirty water related
complaints.
In
addition to cleaning the mains, it was recognised that
a systematically planned program provided the added
opportunity for members of the mains cleaning team to
collect important asset information that will;
| » |
identify
system water quality hot spots; |
| » |
locate
unlined sections of mains; |
| » |
locate
inoperable hydrants and valves; |
| » |
identify
critical valves and hydrants; |
| » |
accurately locate hydraulic zones; |
| » |
transpose
hard copy mains cleaning plans and operational instructions
to digital format for future planning reference;
and |
| » |
update
our Geographical Information System (GIS) with accurate
map base information. |
2.0
ISSUES
The
major issues considered in the decision making process
to implement system wide mains cleaning program throughout
Western Water were as follows:
| » |
A
perception of taste and odours existing throughout
Western Water's system. |
| » |
Customer
dirty water complaints have traditionally been managed
by reactive flushing. Normal practice is that maintenance
teams flush only at the initiation of a customer
complaint. |
| » |
A
systematic mains cleaning program has not been undertaken
since the inception of Western Water in December
1994. |
| » |
Prior
to year 2,000, bacteriological compliance throughout
Western Water consistently failed to meet system
compliance standards. Sporadic instances of low
level (3 to 20) total coliforms were detected throughout
all systems without obvious cause. |
| » |
The
need for programmed mains cleaning was highlighted
during October to December 1999 when a spate of
microbiological exceedance events were reported
at numerous routine customer monitoring locations
throughout the towns of Gisborne, Woodend, Riddells
Creek and Macedon. |
This series of events initiated a controlled study of
a 150mm-diameter section of typical water main in Gisborne
from which the elevated coliforms were detected. The
comparative study of air scouring versus flushing resulted
in a significant amount of sediment containing elevated
counts of coliforms being removed from the section of
main during flushing and air scouring.
In
addition to exposing a dirty system, the study also
confirmed that air scouring was a more effective means
of removing loose sediments and biofilms in mains >100mm
in diameter.
The
result from the study was assumed as being representative
of the condition of water mains throughout all Western
Water systems.
3.0 AIR SCOURING PROCESS
Traditional
methods of cleaning water mains are flushing and swabbing,
however both techniques have some limitations. Flushing
is ineffective in low-pressure areas and large diameter
mains where velocities are low and swabbing can result
in lost, torn or jammed swabs. Air scouring is an alternative
to these techniques, which has proven to be effective
in areas where swabbing or flushing is unsuitable.
The
air scouring technique involves the injection of filtered
compressed air into an isolated section of water main
to generate increased velocity, which is greater than
the minimum velocity required to remove suspended sediments.
Air scouring involves a mix of air and water called
a slug flow. Given a constant supply of air and water
the slug flow strips any loose deposits and some slime
from the pipes. Industry experience indicates that air
scouring uses approximately 40% less water than normal
flushing techniques.
Loose deposits occurring in water mains are the main
cause of customer complaints. The removal of these deposits
certainly gives rise to a reduction in complaints and
improved water quality at customer taps.
Air scouring is designed for water mains less than 225mm
diameter however given favourable site conditions it
is possible to clean 300mm diameter mains.
It is Western Water's experience that air scouring,
if undertaken correctly, is the most effective and efficient
means of cleaning water <300mm in diameter. It is also
recognised that a carefully planned mains cleaning operation
can also provide significant added benefits in optimising
the management and knowledge of water supply assets.
Figure 1: Typical arrangement
for air scouring operations

4.0
AIR SCOURING EQUIPMENT
The air scouring equipment consists of three distinct
features:
| » |
The
compressor |
| » |
The
air cooler |
| » |
The
filtering system |
The
compressor is sized to the pressure rating of the filtration
unit. A 175 cfm compressor is the minimum requirement
to undertake air scouring operations, cleaning mains
up to 225mm in diameter. The volume of compressed air
entering the main is controlled by a series of operating
valves including a pressure-regulating valve.
The
compressed air first passes through a fan driven air
cooler, which greatly reduces the amount of oil passing
through the system in the vapour phase. The temperature
generated from the compressor is typically 60 deg C,
which is reduced to approximately 20 deg C after the
air passes through the air cooler. The air then passes
through a series of three filters:
| » |
Pre-filter
(1 micron): |
The
depth filter removes oil and water vapour. |
| » |
Sub
micron filter (.01 micron): |
The
depth filter removes any bacteria, dirt and dust
particles as well as any remaining oil and water
vapour. |
| » |
Activated
carbon filter: |
Removes any remaining oil vapour, oil and related
taste and odours. |
A
series of gauges indicate inlet pressure from the compressor,
outlet pressure across the filters, mains static pressure
and operating regulated pressure. Filtered air to breathing
standard is then injected into the main to commence
the cleaning process.
Figure
2: Arrangement of equipment for air scouring

5.0 SYSTEM CLEANING REQUIREMENTS
The
estimated total length of mains to be cleaned throughout
Western Water is estimated at 1,500 kilometres. This
equates to 18 months of mains cleaning at average rate
of 4 kilometres of cleaning per day. It was decided
that cleaning operations be conducted over periods of
low demand, which is typically during the months of
April through to the end of October.
Based
on this scheduling, mains cleaning of the entire Western
Water system would be completed over an estimated period
of three years and continued thereafter on a cyclic
basis.
6.0
DETERMINING CLEANING PRIORITIES
At the program concept stage, selecting priority areas
for mains cleaning could not be accurately determined
primarily because of inaccurate complaint data and lack
of IT recording and reporting systems.
Priority mains cleaning was therefore initially flagged
in areas unaffected by water restrictions. Under this
arrangement it was proposed that the townships of Woodend,
Romsey, Lancefield and Sunbury (whilst on Melbourne
water supply) would be scheduled for cleaning using
a mix of air scouring and flushing during 2000 - 2001
financial year. However, with the lifting of restrictions
in November 2000, all towns will now be cleaned progressively
to completion over a three year period and will continue
thereafter on a cyclic basis.
7.0
BENEFITS
The
benefits of implementing of a system wide mains cleaning
program throughout Western Water is as follows:
| » |
Improved
level of service to customers |
| » |
Compliments
the completion of water treatment capital works
improvements |
| » |
Meet
the requirements of our Customer Charter |
| » |
Meet
business plan targets for microbiological, physical
and chemical performance |
| » |
Improved
compliance with 1984 WHO drinking water quality
guidelines |
| » |
Reduced
dirty water quality complaints |
| » |
Contribute
to the elimination of taste and odour problems within
the mains systems |
| » |
Collect
system information that can be used to update system
plans and improve the management and knowledge of
our assets |
8.0
ENVIRONMENTAL CONSIDERATIONS
Mains cleaning using air-scouring technique requires
careful environmental consideration due to the high
concentrations of sediments removed during the process
(estimated three times the normal sediment volumes removed
by normal flushing methods). To comply and go beyond
EPA (Environmental Protection Authority) discharge requirements,
the construction and utilisation of a mobile filtration
unit was introduced. The trailer also provides a means
of diffusing and controlling the water discharged to
the environment.
Photograph 1: Filtration trailer
used to collect discharged sediment and control discharge.

9.0
KEY PLANNING & OPERATIONAL PROCESSES
Preliminary
Operational Checks
Prior to undertaking air scouring it is imperative that
the following operational checks be carried out on the
equipment and the water supply system.
9.1
Air Purification Unit & Compressor
Prior
to the commencement of air scouring operations, preliminary
equipment and system operational checks are conducted
on a daily basis to ensure;
| » |
There
is no debris, etc in the air cooler tube / fins.
Debris can be expelled using compressed air or high
pressure water spray. |
| » |
The
compressor is in good working order and not generating
large quantities of oil. |
| » |
All
connecting hoses are cleaned. Disinfection of all
hoses is undertaken on a regular basis with dilute
sodium hypochlorite solution (4%). |
| » |
Hoses are stored in a contamination free environment
e.g. sealed container. Before connecting the hoses
all lines are blown out with filtered compressed
air. |
| » |
Air
hose safety clips are fastened securely. |
| » |
Air
hose lengths are kept to a minimum to reduce pressure
losses. |
| » |
The
air intake to the compressor is positioned away
from any polluted environment. A polluted environment
may risk a contaminated water main. |
| » |
The
air scouring unit ids located on a relatively level
surface. |
| » |
A
tee piece fitted with a ball valve is installed
on the hydrant connection. This enables the main
to be depressurised of air and make it safe for
the operator to disconnect the hose connection either
from the main, compressor or air scouring unit. |
| » |
All air filters are checked for correct operation
before commencement of cleaning works. |
| » |
The non-return valve is not allowing water to back
feed into air filters. |
| » |
The
lubricator is filled with the appropriate oil. |
| » |
Air
scouring valves are in the correct start up position
before starting the compressor. |
9.2
Water Supply System
A
preliminary site inspection is conducted under strict
supervision of the air scouring team leader to ensure;
| » |
All
nominated valves and hydrants are working and exposed.
|
| » |
Ensure
the area to be cleaned is completely isolated from
service and all isolation valves checked for leakage. |
| » |
All
valve offtakes along the line to be air scoured
are shut. |
| » |
Appropriate
work signage is displayed. |
| » |
All
non-sprung air balls are capped to reduce air pressure
losses. |
| » |
Filter
trailer is safely in position and all connections
are secured. |
| » |
Standpipes
are securely wedged. |
| » |
All nominated discharge points are above ground
level to avoid infiltration of contaminants. |
| » |
Discharge
points do not cause property damage, flooding and
erosion of earth drains. |
| » |
Customer safety and traffic management initiatives
are in place. |
Where necessary, the installation of additional fittings
enables minimal inconvenience to customers and ensures
that the mains' cleaning is conducted in the most effective
and efficient way possible.
All
customers affected by air scouring are advised at an
early stage generally through a card notification drop.
Critical customers which include hospitals, health centres,
schools, doctor and dental surgerys, dialysis patients,
day care centres, kindergartens and public meeting places
are personally consulted to ensure that they are not
inconvenienced and continue to function normally throughout
the proposed cleaning period. Cleaning operations are
restricted where possible to daylight hours between
9.00am and 4.00pm.
Where
hygiene or health related issues arise in premises where
the mains supply water is shutdown for a specified period,
a mobile tanker is made available on a priority basis.
Western Water currently has two "mini res" tanker units
in operation.
10.0
COLLECTION AND RECORDING OF ASSET INFORMATION
The key to successful mains cleaning is having clear,
accurate and detailed sets of operating plans.
The
plans should be very specific and provide wide-ranging
information as follows;
| » |
Segmenting
of areas for daily cleaning operations |
| » |
Location
of critical customers and operating valves |
| » |
Identify special needs customers (dialysis patients,
schools, medical surgeries, etc) |
| » |
Areas
assigned for either flushing, air scouring or swabbing |
| » |
Valve,
hydrant and system operational arrangements |
The
completion of a "field operation log sheet" on a daily
basis is a key means of obtaining critical operational
data that can be used to improve knowledge of systems
operations and assets. The information is collected
on a daily basis and is presented to a planner who in
turn updates system drawings and operational procedures
accordingly. The most appropriate means of updating
asset drawings and planning mains cleaning programs
is through the utilisation of our "Geographical Information
System" or GIS.
11.0
MAINS CLEANING PLANNING ON "GIS"
A
mains cleaning planning application has been developed
on the Western Water geographical information system
(GIS). A digitised plan nominating the sequential operation
of all hydrants, valves, injection and discharge points
are produced on this system. The application involves
the user creating a mains cleaning job. The user selects
a grid area from the operating panel and then applies
symbols / colours to pipes and relevant nodes. Modifying
the graphics assigns injection points, flush points,
scouring points, shut valves and closed valves.
Pipe
colours can be modified according to the status of the
pipe for the relevant job (i.e. flushed, air scoured
or swabbed). Attached to each daily work job is an electronic
version of the field operation log sheet.
The
benefits of planning mains cleaning on GIS are as follows;
| » |
Inoperable
/ faulty / incorrectly located fittings reported
to the planner so that adjustments can be made to
the program and water supply plans upgraded accordingly. |
| » |
Plans
stored sequentially for future reference hence eliminating
intensive re planning. |
| » |
Opportunity
to check asset systems and upgrade GE database accordingly |
| » |
Storage
of critical water quality monitoring and cleaning
operations data |
| » |
Accurate
costing of works |
Figure
2: Planning a mains cleaning program on GIS

12.0
CONCLUSION
A
carefully planned mains cleaning operation primarily
using air scouring technique provides Western Water
with the opportunity to improve the operating knowledge
and performance of its system. The added advantage of
being able to digitise mains cleaning plans and register
updated system information on a GIS database provides
a cost effective means of improving water quality and
system operational data and performance. Information
collected throughout the cleaning program when entered
onto a GIS database encourages an initiative that will
be enhanced over time through the input of additional
asset information. Western Water will take approximately
three years to complete mains cleaning of its system
and will continue thereafter on a cyclic basis. These
initiatives collectively are expected to deliver improved
service level to customers, provide improved drinking
water quality compliance and meet our company business
objectives.
13.0
ACKNOWLEDGEMENTS
The
author would like to acknowledge the valued assistance
and experience of Rick Woulfe, Mains Cleaning Supervisor
and Steve Codd, GIS Coordinator for their input into
this paper.
14.0 REFERENCES
A.F
Elvidge, Water Research Centre (1982), Air scouring
of Water Mains - A Method of Operation.
AWWARF (1992), Implementation and Optimisation of Distribution
Flushing Programs.
AWWA
(1986), Maintaining Distribution Water Quality.
Major Urban Water and Sewerage Authorities of Australia
(1987), Cleaning and Disinfection Practices for Water
Mains.
C Evins, J Liebescheutz, S Williams, Water Research
Centre (1990), Aesthetic Water Quality Problems in Distribution
Systems.
AWWARF (1987), Identification and Treatment of Taste
and Odours in Drinking Water
AWWA ( 1987), Manual of Water Supply Practices - Cleaning
and Lining Water Mains > DOWNLOAD
(pdf
61K)
|