|
Conference Papers | 2001 Conference Papers FERRIC
CHLORIDE TRIAL AT EILDON WASTE WATER FACILITY
Carl Broockmann
- Treatment Engineer,
Goulburn Valley Water
Kirsten Hogan -
Environmental Co-Ordinator,
Goulburn Valley Water
DOWNLOAD
(pdf
34K)
ABSTRACT
Preliminary
investigations into the upgrade of the Eildon Wastewater
Management Facility have resulted in Goulburn Valley
Water undertaking a ferric chloride trial on its trickling
filter system. The trial aimed to determine the suitability
of dosing ferric chloride, with the intention of reducing
phosphorus levels to acceptable environmental limits
for future discharge to waterways (ultimately the Goulburn
River). The trial was conducted between December 2000
and April 2001. This paper aims to present the results
of this trial.
KEY WORDS
Ferric
Chloride (FeCL3), Phosphorus
1.0
INTRODUCTION
The
Eildon Waste Water Treatment plant is a conventional
Trickling filter system that irrigates during the summer
months, and discharges to the Goulburn River at all
other times. While providing an acceptable level of
treatment for solids removal and BOD reduction, allowable
discharge levels of phosphorus set by the EPA remained
difficult to meet.
The lack of available land suitable for irrigation lead
Goulburn Valley Water to seek an alterative method for
the reduction of phosphorous levels within the discharge
water in order to continue discharge to the Goulburn
River.
A ferric chloride trial was decided upon as the best
option for it's low capital cost, ease of set-up, and
low operator attendance. The aim was to reduce total
phosphorus levels from 10.0mg/l to 0.5mg/l in the final
effluent.
2.0 DISCUSSION
2.1 Waste Water Treatment Plant
The Eildon wastewater treatment system is a conventional
trickling filter unit comprising of:
| » |
Inlet |
| » |
Primary sedimentary Tank |
| » |
Trickling
Filter |
| » |
Humus
Tank |
| » |
Digester |
| » |
6
Drying Beds |
| » |
Chlorine
dosing |
The average daily dry weather flow is 0.5ML, which is
predominately domestic waste. The treatment process
utilises sedimentation, aided by aerobic action, for
solids removal, and anaerobic action to stabilise sludge
for drying and disposal.
Pre-dose treated loadings were as follows:
| BOD |
16mg/l
|
| TP |
10mg/l
|
| SS |
39mg/l |
| pH |
7.3
|
New equipment required for the trial consisted of
| » |
Flow
paced dose pump |
| » |
Electronic
flow meter |
| » |
Chemical
storage |
| » |
Chemical
( Ferric Chloride, 15% Ferric) |
| » |
5m pipeline between Filter & Humus tank |
| » |
Flash mixer |
A
chemical dose point just prior to the humus tank was
established to minimise any acidic affect the ferric
chloride may have on the trickling filter and digester
(refer figure 1). The dose pump was controlled by an
electronic mag flow meter installed at the trickling
filter outlet. A flash mixer was installed to mix the
water for optimum chemical dispersion.
2.2
Dosing & Monitoring
Initial Monitoring points were set to fully analyse
the effect ferric chloride had on the treatment process
and the final effluent. The monitoring stations and
their specific tests were:
Table 1: Monitoring Parameters
A
Later sample point was located in the discharge channel
at the exit point of the farm.
Tests were carried out at least 3 days after each change
in dose rate to allow the system to fully adjust. The
dosing rate was initially 20mg/l and progressively increased
by 20mg/l to a maximum of 80mg/. Dose rates stated are
for Fe only
Figure 1: Site Layout

3.0
RESULTS
Prior to the trial, phosphorous reduction in the humus
tank was minimal with an average of 10% removal, from
around 11mg/l to 10mg/l.
The target was less than 0.5mg/l. Initial removal of
phosphorous was promising, with a 50% reduction. This
was backed up with another set of samples indicating
a 43% decrease.
Table
2: Total Phosphorous Levels - 20 mg/L Dose Rate

Subsequent
increases in dosing resulted in indifferent results.
An additional sample was taken at the discharge channel
at the farm boundary
Table
3: Total Phosphorous Levels - 40 - 80 mg/L Dose Rate

Figure 2: Dose Rates V's Phosphorus
Concentration (mg/L)

The
results showed a significant reduction of phosphorous
at the humus tank and an even greater reduction at the
discharge point, indicating floc carry over and further
settlement in the open discharge channel.
The
plant is manually operated and visited once per day
for 1 hour by an operator. The increased sludge generated
in the humus tank had a tendency to float after 12 hours,
and run over the baffle boards. Installing an automatic
valve that operated every 4 Hours may have better controlled
the sludge removal.
Overall
the reduction in phosphorous levels fell well short
of our target and the trial was halted.
3.1 Process Effects of Ferric
Chloride
Floating sludge appeared in the humus tank within days
of trial dosing, which indicated an increase in draw
off frequency was required.
Ferric
chloride significantly effected the pH of the Humus
tank and consequently the final effluent. Adoption of
ferric chloride would require pH correction.
Table
4: Ferric Chloride effect on pH

Figure
3: Ferric Chloride Effect on pH

4.0
CONCLUSION
Ferric
chloride dosing proved to be a significant aid in the
removal of total phosphorous at the Eildon waste water
facility, but failed to meet our objective of 0.5mg/l.
At best, it provided just under a 60% reduction in total
phosphorus levels to a concentration of 3.04 mg/l.
Phosphorus
levels sampled in the discharge channel indicated that
further testing of a more effective sludge removal system
may provide better results. The acidic nature of ferric
chloride significantly lowered pH levels in the humus
tank to the extent that further trials would require
pH correction.
Overall,
the trial, although unsuccessful, provided our technical
and operational staff a greater insight into the chemical
processes of a trickling filter system and the effect
ferric chloride dosing has for phosphorus removal. > DOWNLOAD
(pdf
34K)
|