|
Conference Papers | 2001 Conference Papers CHALLENGING
OPERATIONAL PROBLEMS AT THE BACCHUS MARSH WATER TREATMENT
PLANT
Wes Wittick -
Plant Operator, Western
Region Water Authority
DOWNLOAD
(pdf
519K)
ABSTRACT
The
water treatment plant at Bacchus Marsh, operated by
Western Water, supplies drinking water to the township
at demands of up to 15 ML per day. The plant has recently
encountered a number of operational problems, due to
deteriorated raw water quality.
The
plant is of pressure filter design and was formatted
to treat reasonably good quality raw water. When the
Turbidity and colour increased dramatically, the filter
run times were reduced from 24 hrs to 2hrs maximum.
At this point we looked at dosing Alum into a 40 Ml
raw water storage basin sited at the plant, from which
the filters draw. After some trials and tribulations
it clarified the water beyond expectations and the pressure
filters were pushing out .05 NTU water. As we expected
the fairytale did not last. Taste and Odour problems
were upon us. This paper works through initial control
measures, the addition of Granular activated carbon
to filters and raw water basin cleaning.
KEY WORDS
G.A.C.,
Geosmin. M.I.B., T.C.A.
HISTORY
The
Bacchus Marsh Water Treatment Plant (WTP) was opened
in 1958. Its original configuration was a conventional
type plant, consisting of clarifiers and rapid gravity
sand filters; it also employed the lime/soda softening
process.
In
1985, 8 inline pressure filters were installed and the
raw water source was changed from Pykes Creek Reservoir
to Merrimu Reservoir. Merrimu had thus far been a water
source of good quality, being low in colour and turbidity.
When the pressure filters had been commissioned, the
majority of the original plant was de-commissioned;
still in use are clear water pumps, limil, fluoride
and disinfection facilities.
Decision
time is approaching as to wether the Bacchus Marsh plant
is substantially upgraded or whether Merrimu plant is
upgraded to supply Bacchus Marsh with the Bacchus Marsh
plant being de-commissioned. Upgrades at the Bacchus
Marsh plant would be substantial, as during peak demands,
"shandying" of raw and final water is required; maximum
plant output is 10ML per day whereas demands in excess
of 15ML per day now exist in summer.
1.0 INTRODUCTION
During
the Christmas/New Year period of 1999, the Merrimu catchment
received heavy rainfall, ensuing inflows to the catchment
resulted in turbidity of 100 ntu and colour of 150 tcu.
This drastic reduction in water quality seemed to be
caused by development in the upper catchment, low reservoir
level, drought conditions, logging and possibly a large
dam burst that had been built across a tributary.
At the Bacchus Marsh WTP there is a 40 ML raw water
basin, which is filled from Merrimu Reservoir, the plant
then draws water from this basin for treating. Within
a week of the fore mentioned rainfall, the basin represented
the same quality water as in Merrimu Reservoir. A succession
of operational problems then took place.
2.0
EXISTING PROCESS
The
pressure filters at the Bacchus Marsh WTP are only capable
of treating moderately turbid and coloured raw water.
Timers or turbidity set points initiate filter backwash;
previous to the poor raw water quality, we had filter
run times of up to 24 hours. Afterwards, despite numerous
jar tests, we had filter run durations measured in minutes.
2.1
Previous Works
In 1997/98, a 4km pipeline was installed from the Merrimu
WTP to the Merrimu pump station. Prior to this, a 5
ML clear water tank had been constructed. This new pipeline
is connected to the tank, and flows from it to Bacchus
Marsh, via the Merrimu pump station and break pressure
tank (by gravity flow)
Figure
1: Area Map

2.2
Problems at the Merrimu WTP
The Merrimu WTP treats water for Melton and smaller
outlying areas. These previously mentioned works were
enabled so that the Merrimu plant could supply water
to Bacchus Marsh during the cooler months via the 5ML
storage, although this tank was initially built as a
replacement for an undersized high-level area supply.
At this stage we initiated supply of Bacchus Marsh from
the Merrimu plant. Thankfully, we were into lower demand
times, as the Merrimu plant doesn't have the capacity
in peak demand times. Although easily able to treat
this quality raw water, the extra demand/output was
marked by a large increase in sludge output.
A decision was made to construct 1 large new sludge
bed and install under drains in some of the other sludge
beds, which didn't have them. During these civil works,
we had to move the excess sludge off-site by tanker.
The Merrimu plant kept supplying Bacchus Marsh for some
time, during which time the raw water quality did improve,
but when peak demand times returned, the Bacchus Marsh
plant had to be brought back on-line.
3.0
THE NEXT STEP
For
a time, the Bacchus Marsh plant was able to maintain
filter run times of 2-4 hours, until the Merrimu Reservoir
received further inflows, thus increasing both colour
and turbidity. In addition to this, and as a result
of Merrimu catchment volume increase, the Authority
had decided to lift the water restrictions that had
been imposed 3 years previous.
We then had only one option, which was to pre-treat
the raw water at the Bacchus Marsh plant basin. Although
not happy with the possible eventualities, we set up
Alum dosing facilities with an injection point on the
incoming raw water line. Initially we had problems with
inadequate mixing, but this was overcome with makeshift
in-line mixers installed within the pipe.
After a few days of processing the raw water, enough
turnover had occurred and clarification became evident.
Initial dosages of 100 mg/l were reduced to 80 mg/l
and later 60 mg/l. The raw water basin now acted as
a giant clarifier and was performing 90% of the treatment
process.
Table 1: Raw water characteristics

Water was then drawn from the basin and passed through
the filters with small dosages of alum and polyelectrolyte
added to assist in "polishing".
The resulting turbidity (0.4 NTU) enabled Bacchus Marsh
residents to enjoy water clarity like never before.
Four months passed, after which, taste and odour problems
occurred.
Figure
2: Pressure Filters

Figure
3: Raw water basin (partially emptied)

4.0 TASTE AND ODOUR PROBLEMS
Taste and odour problems commenced in late December
2000, they were earthy/musty/grassy in description.
It was soon concluded that the problem emanated from
the raw water basin. Working against us was the fact
that the basin had not been cleaned since being built
nearly 50 years ago. The clarification within the basin
also compounded all organic matter to the base of the
storage, this in turn allowed sunlight to penetrate
deeper into the water column, this causing additional
problems in itself.
4.1
Initial control measures
We ceased chloramination and commenced chlorination
at an increased dosage, hoping that this would "Mask"
the taste and odours. In addition to this, we carried
out extensive system flushing.
Our next step was to install various forms of aeration;
this was done in an attempt to liberate volatile components
causing the taste and odours. At first, aeration was
carried out in the 15ML clear water storage and, although
the results were noticeable, we decided to move the
aeration process closer to the source. Aeration facilities
were then set up within the raw water basin and the
clear water contact tank located at the Bacchus Marsh
plant, results from here seemed more favourable.
During these initial stages, WSL Consultants Pty Ltd
and Microcosm Consulting Pty Ltd were employed to assess,
quantify and advise on the problems.
4.2 Divers
From our conclusions and Consultant recommendations,
we employed the services of Nordic Diving Services.
The divers spent a few days carrying out various tasks:
| » |
Vacuuming
around plant intake lines |
| » |
Changing
plant "shandy" line to another re-commissioned point
(old plant inlet), which drew water from high water
(floating take-off) |
| » |
Re-configuring
of main plant inlet (raised take-off point 1mt) |
| » |
Optimising
placement of aeration manifolds |
4.3 Results
WSL and Microcosm had been analysing samples from the
onset of taste and odour problems. The works carried
out had resulted in an improvement in measured values,
although, the effectiveness of the aeration was deemed
minimal, so this ceased. Organic analysis of the water
revealed significant concentrations of Geosmin and Trichloroanisole
(TCA) well in the excess of the human taste thresholds
of 5-10ng/L respectively. The actual source of these
taste and odour compounds in the basin was difficult
to pinpoint as a number of organisms such as algae,
fungi and bacteria can produce these compounds that
cannot be used immediately or stored. Anecdotal evidence
suggests that the blue green algae, Oscillatoria
splendida may have been the source of the taste
and odours in the basin due to its abundance and its
well known credentials as a nuisance organism that produces
taste and odour problems.
The
Consultants then recommended the next step of using
G.A.C (Granular Activated Carbon) to combat the problem.
5.0
TRIALING OF G.A.C
WSL Consultants under took lab trials of G.A.C, using
water from the raw water basin. The tests showed that
the G.A.C would be effective in removing the tastes
and odours. Operators were then involved in removing
filter media samples and measuring their depths.
It
was decided to go ahead and replace the Anthracite within
one secondary filter to fully test the viability of
the G.A.C. In late March 2001, this process was undertaken.
This involved an initial soaking period to saturate
the carbon, then "Conditioning" of the filter took place,
during which, back wash rates were measured and backwash
waters analysed for carry-over.
For the first two weeks of operation, we reduced the
backwash rate due to excessive carry-over of G.A.C.
A further inspection of the filter bed found the underlying
sand was not being cleaned properly at this backwash
rate. We then decided to backwash at normal rate and
found carry-over not to be excessive and to be further
reducing at each backwash.
Figure 4: Filter cross-section

Final
analysis from filters with G.A.C reflected lab simulations.
The addition of G.A.C in this application proved to
be a very successful method of removing the taste and
odour.
The
cost of product for this application was $3000 per filter
(1000kg). Media life is expected to be 6 to 18 months,
at which time it would need to be replaced or re-generated.
Table 2: Taste and odour analysis

Hopefully,
the next step, being the cleaning out of the raw water
basin and an improvement in raw water quality, will
negate the use of the Alum dosing to the basin to pre-treat
the raw water and thus stop the progression towards
taste and odour problems. In the event that we did have
to revert to Alum dosing, hopefully with the basin having
been cleaned out, it may take some time before it reaches
a point, which is conducive to taste and odour production.
The
G.A.C would provide a solution if this did happen. Unfortunately,
a problem will arise when shandying, as the shandied
water bypasses the filters and G.A.C.
6.0 CLEANING OF THE RAW WATER
BASIN
The
major task of cleaning the raw water basin was then
undertaken. At the end of April 2001, the Bacchus Marsh
plant was shut down, Bacchus Marsh Township being supplied
with water from the Merrimu plant, and the basin draining
to waste commenced. Steve McKenzie Consulting was employed
to oversee the procedure and Tenders were invited to
carry out the clean out.
On
site disposal of the removed sludge will be possible
as we have cleaned out a number of old sludge beds and
carried out civil works to allow the possibility of
pumping liquid sludges to these beds or to the sewer.

7.0
CONCLUSION
At
the submission of this manuscript, the basin clean out
contract had not yet been awarded. At the moment there
are two preferred tenders. One will use mixers / aerators
/ pumps to de-sludge the basin. The other contractor
will use mechanical means being similar to the clean
out of a large farm dam. The latter would provide a
more comprehensive sludge removal, but there are noise
issues, considering a time estimate on the job of 3-4
weeks.
There has been an improvement in raw water quality with
colour of 85 tcu and turbidity of 12 ntu, although there
is still a high probability that we will have to pre-dose
with alum. When we initially started dosing with alum,
only 4 months passed prior to the onset of taste and
odour problems.
Probably,
the basin had considerable sludge build-up prior to
our alum dosing and this was the catalyst to taste and
odours.
We
are hoping that having the basin cleaned out will allow
us to run the plant for longer than 4 months without
taste and odour problems. Management should have then
decided which plants will be upgraded or perhaps they
will re-visit a pipeline connection to our reticulation
from Melbourne Water to supplement our supply. Consideration
throughout the project was given to the requirements
of the customer charter and business plan targets and
as always, with these processes the customers were kept
informed and the operators involved at each step.
8.0
ACKNOWLEDGEMENTS
I would like to acknowledge the assistance and support
of my fellow team members at the Merrimu and Bacchus
Marsh WTP, Mark Closter and Joan Barry. A special thankyou
to my wife Fiona and daughters Jenna and Sarah for their
invaluable technical assistance to get this manuscript
completed.
9.0 REFERENCES
Dean Comrie - Project Manager of Scientific Services
- WSL Consultants Pty Ltd
Various reports received regarding taste and odour
problems at Bacchus Marsh WTP (2001)
Barbara
Bowles - Microcosm Consulting Pty Ltd
Microbiological Reports > DOWNLOAD
(pdf
519K)
|