|
Conference Papers | 2001 Conference Papers WHY
OPERATORS SHOULD BE INVOLVED IN DESIGN
Rex Foale -
Operations Supervisor, GHD
DOWNLOAD
(pdf
666K)
ABSTRACT
The
"lynch pin" in any Treatment Facility is the Operator.
"Ownership" of an operation is the key to the economical
functioning of the plant. Ownership will only develop
if the Operator is permitted to have meaningful input
into all phases of the design processes. Management
must allow the Operator to spend considerable time participating
in all aspects of the design through the concept development,
design review process, Hazops, construction and commissioning
phases. The cost of this time can be returned in full
over a very short operating period.
KEY WORDS
Design, Operator, Function, Efficiencies, Performance,
Ownership, Pride.
1.0
INTRODUCTION
How often have you heard the saying, "The "suits" have
left the job. Now I'm left to make this damned plant
work." Operators who feel they have been bypassed in
the process of creating the project they now are expected
to run at "world best practice," have a right to feel
aggrieved.
There
will be aspects of the plant that they are not comfortable
with, simple things such as the location of the carpark
and positioning of the night-lights or something more
serious. Perhaps no one bothered to make sure the Operator
completely appreciated the processes and functions involved
in the plant, or understood how these were to be implemented
and controlled.
2.0
THE STARTING POINT
The Operator is often the forgotten ingredient in the
formula used for the design of a new or upgraded water
or wastewater treatment plant. The design of a capital
works project is normally developed as a result of changes
in the demand for treatment, population changes, legislative
changes requiring improved water quality outcomes, a
new industry moving to the supply area and community
expectations.
The physical manifestation of the design frequently
develops as a result of these requirements in a process
of collaborative input between the designer and the
client and some times will include community consultation.
The
detailed design may also develop in effective isolation
as a BOOT scheme or a Design and Construct contract.
All too often the Operator is not involved to any great
extent. After all, they have been employed to run the
other existing plants and must therefore be too busy
to take time off from their duties to attend meetings
on a regular basis, or to wander for hours around a
construction site. This costs money and there is no
direct return obvious to those responsible for containing
costs and establishing KPI's and other bench marking
criteria.
Often then, the Operator is afforded only a cursory
involvement, which is frequently considered sufficient.
3.0
THE FICTION
Didn't
the Authority spend a lot of money training them to
be fully-fledged operators? Don't they now possess the
necessary skills to trouble shoot a Hi-tech plant brimming
with computers, PLC's, SCADA systems, complex chemical
processes and innovative technologies? The Operator
should be able to take all of these issues in their
stride. As a result of all this training, they should
be capable of running the plant after a few hours of
on the job training from the commissioning staff !!
If you have never had the opportunity to observe the
processes of commissioning at the end of a job you could
be forgiven for thinking this would be the case.
4.0
THE REAL WORLD
In reality it is far from that simple. It frequently
takes a large site team of fitters, engineers, chemical
engineers, software and communication engineers, (often
working by remote means) and other trouble-shooters
to solve a whole raft of problems. Frequent physical
and chemical changes, many weeks of hair pulling and
vast amounts of money may be required to commission
a plant and have it run within the parameters required
in the Contract. Optimisation of performance will usually
take longer.
Frequently the designer is an office-based worker sitting
at a CAD machine. Very good at drafting, but often with
little site experience. The more experienced project
manager with the responsibility for checking the design
is usually very busy, and their charge out rates are
high. They cannot afford the time to check perhaps dozens
of design drawings for all the little operational issues
that would make life easier for the Operator so they
concentrate on such items as architecture, structural
adequacy, hydraulic suitability and electrical and control
systems.
I remember the first water facility that I helped design
quite some years ago. It involved three 600 dia. high-pressure
water sluice valves. I had been an architectural design
draftsman for 10 years but to me, these valves were
simply crosses on the drawing.
When
they arrived on site and the docket indicated they weighed
about 4 Tonne each, I looked at the position they were
to installed and wished I had designed the pipe work
so they would be under the 10 Tonne gantry crane that
ran the full length of the building.
Figure.
1: 4 Tonne valves - snugly installed under the mezzanine
floor.

5.0
THE DESIGN REVIEW PROCESS
The
formal review processes conducted through the design
phase of a large project are frequently rushed. Other
issues such as contractual matters and the finances
of the job tend to take priority. When a review meeting
is held, the language is full of engineering jargon
and technical terms that are only fully understood by
highly trained personnel.
The time seems to disappear before operational issues
such as access for taking samples, access for servicing
of equipment, handling of heavy items, working spaces
around equipment to enable dismantling and repair can
be addressed.
Figure
2: Space limitations means more equipment is required
to manoeuvre heavy objects

As
a result, deficiencies in the design can slip through
the review process only to be found by the Operator
when a problem arises and the design causes complications
during rectification works.
How often is it found that to remove a pump shaft some
other machine has to be moved?
Simple issues such as the provision of power outlets
for power tool use around the plant, sufficient hose
points and pressure for washdown, adequate lighting
to enable complicated repairs at night.
Walkways often have steps and sharp changes of direction
that make manoeuvring of wheelbarrows and trolleys impossible.
Even though the width of a walkway at 600 mm is wide
enough to allow people to walk along them, it makes
it almost impossible to carry buckets or tools on them.
Speaking to school groups etc, requires a very loud
voice to reach the people at the back.
Figure
3: Nice, but narrow walkway

One
simple feature often overlooked is the provision of
drain valves and the controlled discharge of drainage
from tanks. A tank may only require to be emptied once
a year or so but the use of pumps in above ground tanks
and running of hoses to a safe discharge point can be
a heavy and frustrating job that may take days to oversee,
moving pumps about, re-fuelling, cables, generators
etc. A valve and drain may only cost a few dollars,
pumping can cost many dollars every time.
Figure
4: Not the fastest way to empty a tank of sludge

Figure
5: How many hands are required to climb a ladder and
carry a toolbox?
 |
Have
you ever tried to carry a toolbox, or anything at
all for that matter, up a vertical ladder? If you
have, you quickly realise why they are not popular.
|
Figure
6: Access to this valve may be classified as less than
ideal

6.0
TRANSITION TO NEW TECHNOLOGY
It
should be remembered that there are many operators in
the industry who have previously worked as truck drivers
or mechanics or on pipe maintenance who are now being
expected to run very sophisticated technically advanced
treatment plants.
For
those not familiar with them, SCADA systems can be daunting.
The thought that someone can run a treatment plant from
their bedside table takes some getting used to. Control
Systems should therefore be set up in the clearest format
possible and provide all the information that the Operator
requires. User-friendly systems are essential.
While
this approach makes an experienced Operator's life a
little easier, it also makes the training of a new Operator
a much simpler task.
It should be remembered that Operators can get sick,
take holidays and sometimes take RDO's. The replacement
Operator may not be as familiar with the installation
and in an emergency has to be able to take over the
operation immediately. It may be that the replacement
personnel are from the office and may have only visited
the plant occasionally.
The
procedures to operate the plant effectively therefore
must be as simple and clearly documented as is practical.
Every item should be fitted with a clear and fully descriptive
label.
Another
problem of significance is the geographical layout of
the plant.
Figure
7: Not the best route to the filters. Noise in the Lab
is a likely problem here

It
would appear little thought has been given to the distances
and pathways an Operator needs to travel when collecting
samples or inspecting the various components of the
plant. eg. The door to the office is frequently at the
opposite end of the site to the entry door to the filter
cells or the blower room can only be accessed by walking
around a building, and/or, travelling through three
other rooms. Over the past 2 years, I have visited a
couple of dozen water and waste water treatment plants
and found these types of issues to be present at all
of them.
An Operator whose plant has a large number of these
design problems will quickly become frustrated. It would
not be surprising then if the performance of those plants
did not consistently meet the required criteria.
7.0
OPERATOR INPUT DURING DESIGN AND CONSTRUCTION
It
is essential that the project management team involve
the Operator in the design process by facilitating specific
operations-focussed discussion with the Operator. Input
from the Operator must be given due recognition. It
may not always be expressed in the most appropriate
manner but the design team must persist until any suggestion
is clearly understood. Operators must also persist until
they are comfortable that their queries have been answered
to their satisfaction. Everyone should also remember
the old adage that there is no such thing as a dumb
question!
Providing
the suggestions put forward by the Operator are not
outrageous, they should be implemented. It is cheaper
to widen a walkway by 150 mm prior to construction than
to determine later that there are OH&S issues with what
was built and removing, say, 50 metres, adding the required
extra width, and re-installing the whole thing again.
There
is also no point saying "yes" at these meetings and
subsequently deciding not to proceed. The stories often
heard are "When I told them, they said it is too late
now the job is finished. It would be too expensive to
fix now. Put up with it for now and we will fix it in
stage 2."
It is true that many Operators are now given more exposure
to the various stages of the design process these days.
However, they can often be brought in so briefly that
the matters under discussion appear irrelevant, too
technical or simply boring.
Time may be too short, or management cannot afford their
Operator to be away from their normal duties, there
is always an emergency somewhere else that requires
their presence. Management should make every effort
to provide other staff to cover the time the Operator
is involved in these sessions. I believe it is cheaper
to spend the money now to have an Operator heavily involved
in design than run the risk of them becoming uninterested,
frustrated, confused, unable or unwilling to operate
the plant at its full potential.
Arrangements should be made for the Operator to visit
other plants using similar processes and systems and
to spend time with the Operator of that plant as they
carry out their normal duties. This allows the Operator
to learn the idiosyncrasies of the process and systems
and to become familiar with the methodologies involved.
Overnight stays may be needed and more than one trip
should be allowed for.
The Operator must attend site regularly during construction
to witness how various components are assembled. This
should be for a number of hours at a time as no one
can pick up the knowledge required in 10 minute visits
every week or so.
This attendance becomes more crucial during the final
commissioning of the works. This is the time when problems
with the new works are identified and corrected and
attendance should be for whole days as appropriate to
the work being undertaken at the time. Depending on
the size of the project, this period could require the
operator to be on site for weeks.
The knowledge of how problems are corrected is invaluable
as the plant "beds in" and it enables the Operator to
better describe the non-conformance to others during
the defects period of the contract, and beyond.
Contractors
and engineers will have difficulty planning the appropriate
corrective actions if the description of the issue goes
something like this "What's the problem? .It's stuffed!!
. What is really wrong with it?..It's really
stuffed !!
An Operator who feels they have been an integral part
of the design and construction process will, I believe,
develop a better understanding of the operational requirements
of the finished plant and a better appreciation of their
role in ensuring the plant always runs at its full potential.
Operators
will be able to better manage the control systems as
installed and be able to interpret the outputs of the
many instruments included in modern treatment facilities.
Operators will also feel more confident in handling
any event outside the norm, and are more likely to make
the right choices when they fully understand the purpose
of the individual parts of the plant as well as the
functions of the whole installation.
8.0
FINANCIAL IMPLICATIONS
Once
the plant is operating under the control of the designated
personnel, large savings can potentially be realised.
Recent personal experience has shown that if the Operator
has neither the time, understanding nor inclination,
operational setpoints are often selected to cover the
worst-case scenario.
Mechanical
processes are often set at maximum, as this will get
the job done faster. Running a plant beyond its optimum
setpoints may result in equipment failure and fouling
of equipment, tanks and other items that can inhibit
overall plant performance. The resultant down time and
the excessive number of call-outs may be expensive,
not to mention the cost of a breach of the discharge
license.
Adjustments
to the plant are often re-active and sometimes to the
extreme, with many parameters being changed at the one
time. The end result is a plant that does not perform,
and the reasons why are difficult to determine because
of the number of changes, and the size of each change.
In
a Dissolved Air Flotation and Filtration (DAFF) water
treatment plant, large volumes of treated water may
be lost through extended float and backwash times and
associated flow rates. This is water that has already
been dosed with expensive chemicals, electricity has
been used to pump the water and excessive flow rates
contribute to unrecoverable costs with each recycle.
The
higher flows may also overload the sludge handling facility.
Excessive dosing of Polyelectrolyte can lead to the
blinding of the filter media. This will reduce filter
run times and increase the need to backwash due to steeper
headloss curves. This adds to the volume of lost treated
water.
All to produce a "clean" tank surface when all that
is required is to keep the blanket moving.
To
put some of what has been said into perspective, a modern
DAFF water treatment plant processing reasonable raw
water will require, say, an Alum dose rate that will
vary between 30 & 60 mg/L. I have found recently a number
of plants regularly dosing at 100 mg/L and as high as
150 mg/L simply to cover fluctuations in raw water quality
in order to minimise operator attendance and to avoid
the need to conduct jar tests or to spend time adjusting
rates to optimal levels.
9.0 POTENTIAL COST SAVINGS
At
a plant with an average inflow of 10 ML/day dosed with
Alum at 100 mg/L, this would represent an excess of
Alum dosed of some 500 kg/day. Over a year, this is
an unnecessary waste of about 180 Tonne of Alum, not
taking into account the other products involved such
as flocculation aids and pH correction chemicals.
At
current regional delivered prices this waste is in the
order of $ 38,000.00 for Alum alone - sufficient savings
to justify a higher level of investment in the operations
staff before the plant is placed on line.
In wastewater tertiary treatment plants where the dosing
rates are often much higher, more chemicals with higher
purchase prices may be involved plus other materials
such as flocculation aids, pH control and other proprietary
products, the potential savings from optimisation of
the plant performance become even more significant.
The
potential costs of chemical wastage etc in a 20 ML/day
tertiary wastewater plant could exceed $ 500,000 per
annum. These surplus chemicals will usually be removed
from the water stream as a sludge.
Treatment,
disposal and the environmental aspects of such sludges
are a matter for further discussion by others.
It
would appear from the costs involved in water and wastewater
treatment that a good Operator is literally worth his
or her weight in gold.
10.0
CONCLUSION
I believe that a moderate investment in the operational
staff who will be responsible for the direct operation
of a sophisticated treatment facility will have the
potential to provide large returns from process optimisation
that can be many times the value of the initial outlay.
Informal
training through the design reviews, construction and
commissioning phases of a project, particularly when
combined with more formal training in certificate courses
tailored specifically for the industry, will also provide
long term benefits for the employer on site and beyond
the boundaries of the treatment facility.
11.0
ACKNOWLEDGEMENTS
Those
Authorities that have allowed me to take the photographs
used in this article, thank you. > DOWNLOAD
(pdf
666K)
|